Meeting record · September 28, 1998

Meeting Notes

Hydrological Modeling Subcommittee (HMSC)

September 28, 1998

10:00 – 2:00 pm

Nevada Colorado River Commission Conference Room

  1. Introductions and Housekeeping
  2. Jan Matusak of Metropolitan Water District of Southern California offered several technical revisions to the draft Meeting Notes from the HMSC Meeting of August 19, 1998. Those revised meeting notes will be distributed to Subcommittee members for action at its next meeting.

  3. Briefing from Biological Subcommittee
  4. Marty Meisler provided an update on the activities of the Biological Subcommittee and reported on its meeting held on September 16-17th in Phoenix. It was suggested that the Bio Subcommittee and the Hydrologic Modeling Subcommittee collaborate on developing recommendations to the Work Group for the Pilot Project short-list.

  5. Update on Action Items from 8/19 HMSC Meeting
  6. Chris Harris reported that they met with Gary Bryant, USBR Yuma Project Manager and he agreed that his office would provide assistance as necessary to the MSCP.

    The next steps are to draft and send a letter to Reclamation with the Subcommittee’s "wish list" from Chris Harris and Mike White as to what data the Subcommittee is interested in, followed by a meeting in Yuma to map out a strategy for gathering that data.

  7. Modeling Paper Discussion

An in-depth discussion of assumptions, issues, objectives modeling needs and methodologies took place during initial consideration of modeling discussion papers. The HMSC reached consensus on both the objectives of the modeling effort and recommendations for consideration by the Work Group.

Consensus Point #1:

The HMSC agreed by consensus that the objectives of the modeling effort are two fold:

1. To support development of conservation elements (mitigation) of the Plan; and

  1. To support the impact analysis of all conservation elements in total (NEPA compliant).

It also agreed that assuming these objectives are in fact valid, that an analysis of daily "information" is useful and should be undertaken. Regarding the use of a 24-month model, those who felt that its application would be useful indicated that such a study should be undertaken. Those who did not find it useful indicated that the time and dollar costs of such a model were not high enough for them to withhold their support for moving forward and agreed to run the model.

Consensus Point #2:

Based upon the preliminary understandings noted in #1 above, the HMSC adopted by consensus the following recommendations for transmittal to the Work Group:

  1. Undertake a 24-month study of 6.5, 7.5 and 8.5 Million Acre Foot (MAF) demand schedules using "most probable hydrology";
  2. Undertake an analysis of daily historical data (e.g., flow, precipitation, diversions, etc.);
  3. Undertake water surface profile modeling (e.g., site- and/or reach-specific); and
  4. Defer long-term probabilistic modeling and analysis until efforts can focus on site-specific and planning area needs.

Responsibilities for implementing recommendation #1 were assigned to Bruce Williams and Terry Fulp of the Bureau of Reclamation and Dan Epstein of RTi. Responsibilities for recommendation #2 were assigned Ogden and the Hydrologic Modeling Subcommittee. Responsibilities for implementing Recommendation #3 were assigned to Ogden/RTi, and the HMSC. Odgen/RTi and the Bureau of Reclamation (Bruce Williams and Terry Fulp) were given the responsibility of reporting back to the HMSC regarding recommendation #4 at an appropriate milestone early in 1999.

  1. Other Matters
  2. None Discussed

  3. Next Steps
  1. The Bureau of Reclamation and RTi will distribute modeling and analysis results from Recommendation #1 above to the HMSC when a draft has been completed (projected for December 1998).
  2. Marty Meisler will schedule a Biological Subcommittee meeting to identify biological objectives for the upcoming Pilot Study.
  3. The Bureau of Reclamation (BuRec) and Odgen/RTi will follow-up with BuRec’s Yuma Office to obtain data necessary for implementation of Recommendations #2 & #3 above.
  4. The HMSC and Odgen/RTi will seek input from the Boulder City Office of the Bureau of Reclamation prior to undertaking Recommendation #3.
  5. The next meeting of the Hydrologic Modeling Subcommittee is scheduled for Wednesday, December 2, 1998 from 10:00 am – 2:00 pm. in Las Vegas at a location yet to be determined.
  1. Adjourn