DRAFT AGENDA
Compliance Subcommittee
April 10, 20019:30 AM-3:00 PM
2nd Floor Conference Room
California Colorado River Board
770 Fairmont Avenue
Glendale, California
1.Introductions and Announcements:(Bill Werner)
2.Critical Path Items
A.Update on EIS/EIR/BA Baseline Modeling AssumptionsInformation Item
Jayne Harkins/Tom Shrader will
provide an update on discussions regarding the modeling assumptions for the
EIS/EIR and BA as discussed during between meeting conference calls.
Handout:Updated Modeling AssumptionsHandout from Jayne Harkins
Desired Outcome:Update members of the Subcommittee
B.Biological Assessment (BA) Outline of ContentsInformation Item
Tom Shrader will provide an update
on revisions to the Outline/Table of Contents for the BA and answer
questions.
Handout:None provided
Desired Outcome:Update members of the Subcommittee.
C.Update on EIS Chapter 2Status Report
Tom Shrader will provide an update
on changes and revisions to Chapter 2 of the EIS
Handout:
Desired Outcome:For Information Purposes Only
D.Revisions to the “No Action” AlternativeStatus Report
Marty Meisler
will review comments and revisions
made to the revised“No Action”
Alternative paper.Handout:
Desired Outcome:Consensus Recommendation to the Steering Committee at their next meeting on revised wording of this portion of the NEPA/CEQA document
3.Update on Schedule of Deliverables and Compliance Subcommittee Meeting Dates/Decision Points
Bill Werner, with the assistance of the Facilitation Team and Technical Consultant will outline the deliverables from the Technical Consultant that warrant Compliance Subcommittee review and comment and develop a schedule of meeting dates and topics over the next six months.
Handout:Updated Work Plan Schedule
Desired Outcome:Refined schedule of meeting dates and topics for May – Sept. 2001
4.Status Reports, Briefings and Information Updates
A.Section 7/10 Meeting and Update from Implementation SubcommitteePaul Selzer
(No Action Required)
B.Briefing on Extending Biological Opinion Consultation deadline Laura Herbranson
(No Action Required)
C.Update from Ft. Mojave Tribe re Agricultural Water UseJohn Algots
(No Action Required)
D.Update on NCCP Planning Agreement (From
Implementation Subcommittee)Paul Selzer
(No Action Required)
E.Comments on Indirect Effects Paper Joe Vanderhorst
(No Action Required)
5.Next Steps, Action Itemsand Adjourn (5-10 min.)