Work Group Meeting

Commissioner’s Meeting Room, 5th Floor

McCarran International Airport

Las Vegas, Nevada

February 26, 199

Meeting Notes

Agenda Item #1 Welcome and Introductions. The meeting was opened by Vice Chair Phil Lehr.

Agenda Item #2, Discussion of MSCP Work Group Procedures and Process:

    1. Time Management and Decision Making: Alana Knaster summarized the facilitation team’s approach to making meetings more effective as outlined in the material provided with the Agenda. The Work Group approved the procedures and process with minor wording changes including clarifications that all policy decisions of the Work Group be labeled as such and that the Facilitators coordinate with the POC as well as the Work Group Chair and Ogden in identifying products and issues to be addressed by the Work Group rather than the Steering Committee. (See attached revised text.)
    2. Role Distinction of Steering Committee, Work Group and Administrative Subcommittee: John Jostes outlined a discussion paper addressing the Roles and Responsibilities of the various committees, groups and subcommittees involved with the LCR-MSCP process. After discussion and minor wording changes, the Work Group forwarded by consensus the discussion paper to the Steering Committee for their adoption at the March 26, 1998 Meeting (See attached revised text.)

      The Work Group also reviewed a discussion paper entitled "Subcommittees of the Work Group" and adopted these guidelines by consensus.

      The Work Group also reviewed a discussion paper entitled "Administrative Committee" developed by the facilitation team at the request of the Steering Committee. After minor wording changes, the Work Group forwarded, by consensus, the discussion paper to the Steering Committee for their review and adoption at the March 26, 1998 meeting. In its review, the Work Group suggested that all meetings of the Administrative Committee be noticed to the full Steering Committee and Work Group.

Agenda Item #3 Ogden Team Update:

3A. Summary Presentation on Implications of Data Gaps: Michael White of Ogden reported that Ogden now has received the Arizona data regarding species and is awaiting data from Nevada. The Vegetation Community maps are 1994 data and not yet geographically rectified. Currently this material is being revised. Upper area data will be ready in the spring; the stretch between Hoover Dam to the international border will be ready in summer or fall 1998. He noted that there exist data gaps concerning recreational data, particularly that related to boating and bird watching. However, sport fishing data is adequate. Mike White indicated that he would provide a laundry list of missing data (i.e. ortho quads) to Chris Harris for his distribution to other work Group members. Additional data will then be provided to Dr. White by March 13, 1998.

Ogden indicated that they did not have any additional information for consideration at the March 26th Steering Committee meeting.

3B. Milestones and Schedule for Product Review: Mike White distributed a detailed schedule with milestones and task duration for review by the Work Group. He indicated that he anticipated filling the data gaps during the period between March and June, 1998 and would report back to the Work Group regarding the implications of those data gaps at the July meeting. The current schedule indicates that the EA and EIS for the MSCP will be developed concurrently with MSCP development. Ogden indicated a preference to develop a list of conservation elements by September 1998 that would serve as the basis for drafting strategies. The project schedule was reviewed by the Work Group and will be provided to the Steering Committee at their March 26th Meeting.

Laura Herbranson suggested that a Program Subcommittee be created to work directly with Ogden and the Facilitators to integrate scheduling of products into Work Group activities and agendas, as well as to track schedules, and to make sure issues are raised in a timely manner. In the discussion that ensued, it was suggested that a monthly meeting or conference call take place to develop tentative agenda topics, and review monthly progress. The Program Subcommittee was established to include the Work Group chair and the chairs of each of the ad hoc subcommittees of the Work Group. An initial conference call was set up for Monday March 16th at 3:00 PM Arizona time and 2:00 PM California/Nevada time. Chris Harris will initiate the call; participants will include representatives of the Facilitation team, Ogden, the Program Subcommittee and other interested parties as space allows.

3C. 100 Year Flood Plain Line Identification: Mike White indicated that it was extremely difficult to precisely delineate the 100 year flood plain line and raised questions as to whether this level of precision was desirable at this time. During the discussion, it was noted that some property owners might wish to know whether their land is within or outside the Plan boundary; however, since the primary land owners are government agencies, and it is unlikely that there will be many requests for individual landowner taking permits, Work Group members decided that Ogden be allowed flexibility in the boundary delineation task. It was the consensus of the Work Group that Ogden not focus on a specific definition of the flood plain line for now and provide greater precision as needed. However, the outer boundary would be defined based upon the 190 USGS quadrangles. This approach could establish an "initial" line for take that would probably change as Ogden’s work proceeds.

Agenda Item #4 - Biological Subcommittee Review and Meeting Preview – Vegetation Classifications Summary: Michael White of Ogden reported that the Vegetation Classifications summary is near completion and will be distributed shortly. It will be the subject of the biological Subcommittee meeting scheduled for April 16th in Phoenix at the Department of Water Resources.

Agenda Item #5 - Peer Review Draft Proposal: Larry Purcell, Chair of the Peer Review Subcommittee summarized the six key elements of the proposed Peer Review Guidelines for the Work Group. Minor wording changes were suggested including changing references to external and internal review to formal and informal review.. It was also suggested that informal review would include consultation with qualified scientists by Ogden or the Steering Committee. The Work Group proposed that language be added requiring all original comments received by peer reviewers be forwarded unedited to the Steering Committee along with the recommendations of the Work Group. The Work Group forwarded the revised Scientific Peer Review Guidelines, by consensus to the Steering Committee for their review and approval at the March 26, 1998 meeting.

Agenda Item #6 – Review of Outreach Strategy: Lynn Machon provided the Work Group with a brief update on the public outreach strategy. She reported that the Public Outreach Subcommittee met the previous week and discussed potential outcomes (e.g. lowering lake levels) and their implications. The Subcommittee developed a comprehensive media list for use during the MSCP process. She invited Work Group members to contact her for copies of the Subcommittee meeting minutes.

Agenda Items #7 – Discussion of Facilitation Team’s Revised Convening Report: Alana Knaster summarized the process utilized to revise the convening report and issues paper and outlined the options available for addressing the issues pertaining to the scope of the plan. Considerable discussion took place on the issue of the Definition of the "Project". Key concerns centered around whether the project should be defined as the adoption of the MSCP or federal actions (FWS) regarding the issuance of a 10A permit, and the nature of environmental review under NEPA, as well as adding an additional option to cover Bureau of Reclamation River Operations. The Work Group deferred making a recommendation on the language regarding the definition of the project until they received a presentation by NEPA specialists on the concept of MSCP and NEPA requirements. Subsequent to that presentation, the Work Group will finalize its recommendation and forward it to the Steering Committee for their review and consideration.

Regarding Species Inclusion, the Work Group added language to the discussion as a third option, proposed as follows: "3. The species list will be the result of Steering Committee discussion on the extent of desired regulatory coverage for listed and unlisted species, balanced by the cost of inclusion and the availability of data." The Work Group forwarded, by consensus, the remaining components of the Revised Convening Report for consideration by the Steering Committee including:

    1. Issues Pertaining to the Scope of the Plan (as revised) with the exception of "Definition of the Project"
    1. Process Structure and Schedule
    2. Decision Making Process
    3. Representation on the Subcommittee

The Facilitation team also reported on the status of their outreach efforts with regard to making recommendations to the Steering Committee for filling the remaining seats on the Steering Committee.

Agenda Item #8 – Final Biological Opinion – Status of RPAs and Yuma Update: Laura Herbranson reported that the Bureau of Reclamation (USBR)is working with the Fish and Wildlife Service (FWS) to incorporate the comments by the Solicitor’s Office into a revised Draft of USBR responses to Comments on the Biological Opinion. That redraft should be ready to release in approximately two weeks (mid March 1998). She also reported that USBR would be taking FWS and Ogden on a field review of the lower river in late March. She also provided a briefing on the status of RPAs 13, 14 and 11. Mike Walker, also of USBR provided additional details on RPA 14. Issues raised during the discussion included if and in what situations is there a nexus between FWS and USBR opportunities for species protection, and how the RPAs dovetail with the long term MSCP process.

Other Items – Web Site Development: Phil Lehr, Chair of the Web Site Subcommittee summarized the efforts of the web site Subcommittee and reported that a domain name had been obtained. The domain name for the program will be: http//www.lcrmscp.org. He also noted that because the Nevada CRC has offered to sponsor the site, there will be no costs for the MSCP Process to incur. He invited Work Group members to provide feedback regarding organization of the web page and provide documents for posting. He also indicated that the web page would make use of Adobe Acrobat as a reader so that individuals utilizing the full range of platforms could access, download and read materials posted on the page.

Agenda Item #9 - Long-Term Funding Subcommittee Update: This matter was continued to the March 26th Work Group Meeting.

Agenda Item #10 Review of Next Steps and Action Items – This item was delegated to the facilitation team for distribution to Work Group Members via Fax as a follow-up to the meeting.

The meeting was adjourned at approximately 3:40 PM by Chairman Chris Harris.