MEETING NOTES
MSCP STEERING COMMITTEE
OCTOBER 28, 1999
Agenda Item #1Review of Agenda
A report from the Alternatives Subgroup was added to the agenda.
Agenda Item #2 Approval of Meeting Notes of September 23, 1999
With some minor edits provided to the facilitation team, the meeting notes were approved by a consensus.
Agenda Item #3 Public Comment - There were no comments from the public.
Agenda Item #4 Program Scheduling and Cost Issues
A.Alternatives Development
Laura Herbranson distributed a copy of an approach for obtaining information to guide the development of alternatives.In addition to the conservation opportunity group chaired by Chris Harris,the Steering Committee approved the establishment of six additional groups:
--ag land conversion and land acquisition
-- flood plain management
-- fire management
-- native and nonnative aquatic species
-- power
-- water acquisition
SixSteering Committee members volunteeredto serve as chairs/coordinators at the request of the PSC.Each group is charged with developingoptions, evaluating the pros and cons associated with each option and as appropriate, providing recommendations to the Steering Committee. The input from all of the groups will be integrated into NEPA/CEQA alternatives.
( contact the facilitation team if you wish to participate on a group and have not volunteered as yet).
Issue papers are to be submitted to the Program Subcommittee by January 14th.The issue papers and a synopsis of the recommendations will be presented at a two day workshop in January.Based upon Steering Committee input, a set of alternatives will be developed and submitted for public scoping.
B.Schedule/Milestones
The PSC presented a revised set of schedule milestones with a projected completion date of July, 2001.The proposed schedule represents a six month slip in the original MSCP schedule.There was a lengthy discussion of the potential problems that would result including the importance of the interface of the MSCP with other regional programs and questions about whether there were possible time savings that could be identified at this time.PSC members noted that next 6 monthschedule is ambitious and that it would be difficult to shave off any further time until there is a draft preferred conservation plan ( early April).
The proposed schedule was adopted by a consensus with the understanding that there should be an ongoing effort to find opportunities to shorten the overall MSCP process timeframe.
C.Budget
Fred Worthley distributed an updated status of accounts.The PSC needs additional time to review the current process budget.The Steering Committee reiterated its request for an analysis as to whether there are any future unanticipated expenses that would need to be considered by member organizations.This issue will be considered again at the December Steering Committee meeting.The PSC was asked to consider whether there are additional funds needed for the consultant teams to complete their work, or for USBR additional tasks (such as the staff time dedicated to the opportunity areas analysis).The Steering Committee also requested that the PSC consider whether or not to recommend funding additional ICMs given the schedule slip and the importance of providing conservation actions on the ground until there is an MSCP in place.Laura Herbranson noted that USBR has revised the cost estimate for the work associated with the opportunities area analysis and will be able to cover this out of current funds.
Agenda Item #5 Process Proposal
The Steering Committee approved the facilitation team’s proposal for modifications to the MSCP process by a consensus.This includes a reduced role for the Work Group and greater emphasis on subcommittee work.These changes require ensuring that meeting notes and documents from all of the subcommittees available to the Steering Committee and places more responsibility on Steering Committee members to coordinate the input provided by staff who may be attending these sessions on behalf of their organization.
Agenda Item #6 Status Report on Meetings with Mexico
Laura Herbranson reported on a subsequent meeting with Mexican officials regarding opportunities to collaborate.She noted that the current approach of the group will be to attempt to coordinate regarding studies that have already been proposed and to search for funding opportunities.
The Director of the Biosphere Reserve, Jose Campoy, indicated that he would like to attend the next session of the Steering Committee to make a brief presentation on goals of the Biosphere that might be of interest to the MSCP and to learn more about the MSCP process.The Steering Committee agreed to extend an invitation to Mr. Campoy for the December 3 meeting.
There was also a brief follow-up discussion among the members regarding the need to coordinate with other forums on issues of concern to the MSCP.Phil Lehr referred to salinity talks that EPA is spearheading that would be important to track.No action was taken.
Agenda Item #7 Status Report from the Compliance Subcommittee
Bill Werner submitted a summary of recent subcommittee discussions.He provided an update on the discussions on “indirect effects” which is one of the most complex issue that the subcommittee is currently addressing.Bill Swan has provided some initial thoughts on the issue that he has shared with Tom Wilmoth and the lawyers group.However, there still are major differences of opinion that need to be resolved.Jeff Kightlinger has agreed to draft a text to guide subsequent discussions.The group is hoping to reach some decisions with Interior representatives on this issue and on “tiering” by early January.
Agenda Item #8 Status Report on Conservation Opportunity Areas Study
Chris Harris has distributed a summary of the deliberations of his group which hopes to conclude its investigation of the initial 7 areas by November 30.The team is looking at open water, marsh and other habitat types re what species will benefit, the amount of water necessary to provide these benefits and costs.The remaining site work should be concluded by mid-January.The data will be submitted to the MSCP at that time; however, the team will develop a more elaborate summary report by March that can accompany the MSCP as appropriate.
Agenda Item #9 Briefing- Implementation Issues
The subcommittee is awaiting a detailed response to its proposal re “assurances” from DOI by November 9th.The response will then guide subsequent committee deliberations.A meeting is planned in D.C. on November 16th to discuss some of these issues in person with agency staff.
A hearing has been set on the Chafee Bill.The MSCP has been asked to send a commentator.Pay Mulroy has agreed to play this role for the MSCP.Jeff Kightlinger has agreed to develop talking points regarding the uniqueness of the process.
Agenda Item #10 Status of Covered Projects
Tom Shrader provided a summary of the key comments he has received thus far.He still is awaiting information from BIA, NPS and revisions to BLMs list.He intends to revise the document, shorten it and make it more user friendly.Some of the details now in the text would be placed in an appendix.The group that is grappling with covered projects is scheduled to meet on November 22nd.Discussions will focus on state covered actions.Tom agreed to develop a list of the issues that participants need to come prepared to discuss at that meeting.
Alana Knaster reiterated the importance of the milestone, December 3, for approving the MSCP “List of Covered Projects” and reaffirmed the Steering Committee’s support for reaching closure on this issue at the December 3rd meeting.This will require cooperation on everyone’s part.
January 7th has been set as the target date to provide a quantification of covered projects; January 28th has been targeted as the date for Steering Committee review of the detailed description of covered projects.Slippage in these dates will affect the overall schedule.