Draft Meeting Notes
Implementation and Long Term Funding Subcommittee
August 20, 1998
Discussion of the Seltzer paper, Incidental Take Authorizations: Section 7 Alone or an Integrated Section 7 - Section 10 Approach"
The paper provided the basis for an extensive discussion of the pros and cons of using various approaches including Section 7, a Section 7-Section 10 approach, and a "super charged Section 7" approach. There was a general sense that an integrated approach had many advantages, but there was a concern voiced that the "no surprises" provisions had been used to give a level of assurance is some plans that were now being challenged in the courts. There was also a general sense that the "super charged Section 7" could be made to work but to do so would require that some means of providing necessary assurances to many of the participants be demonstrated.
There was general agreement that it would be useful to develop a matrix that compared the three options as applied to the 10 parameters suggested in the Seltzer paper. This would provide a good briefing tool for the presentation to the Work Group and for the proposed workshop at the September Steering Committee meeting.
Implementation Structure
There was general agreement to recommend the structure, as illustrated in the attached figure. It was decided that the "Program Management Committee" (a working title for the executive body) should have approximately the same configuration as the existing Steering Committee, albeit with slightly fewer members. The following composition was discussed:
States (3 members each) 9
State wildlife agencies
State power interests
State water users
Federal (2 members) 2
Bureau of Reclamation
Fish and Wildlife
Tribal Nations (2 members) 2
Colorado River Indian Tribes ?
Hualapai?
Environmental/conservation interests 3
one per state?
Local/recreational interests 3
one per state?
There was considerable discussion of the importance of ensuring the attendance of the actual "Implementation Committee" members. It was suggested that this might be accomplished by having only one or two meetings per year, by getting a personal commitment from individual members to attend at the time they become members and, perhaps, other means.
Housing the Implementation Structure
There was an initial discussion of where the structure should be housed. Two general alternatives were identified: 1) a separate, free-standing entity and 2) housed within the Department of Interior. A number of advantages and disadvantages related to each were discussed, including access to administrative services, perceived independence, "ownership", access to decision-makers, etc.
It was agreed to table this discussion of where the structure would be housed to the next Subcommittee meeting but to forward the recommendations on the structure itself to the Work Group.
Draft Implementation Agreement
David Moser distributed and "walked through" the memo dated August 17, 1998 and titled "LCR MSCP - Implementation Issues". He pointed out that it was written with the expectation that Section 10 would be part of the process. He also noted that the outline should be regarded as a "living document" both updated as the planning proceeds and used to check progress on various elements.
Process for accommodating future projects from non-MSCP parties
Based upon a report from the Projects List Subcommittee that they had not yet reached agreement on the nature of projects to be covered and how they would be described, it was agreed that this discussion should be postponed to the next meeting.
Long term funding discussion
Jun Onaka distributed figures that he was working on in an attempt to develop a baseline spending profile for predicting long term funding needs. He is expecting additional data and asked that members of the Subcommittee contact him with any interpretive information that would help to better interpret the data that was distributed. A more definitive report will be available at the next meeting.
Materials Distributed:
- "Lower Colorado River Environmental Studies (1985-present)", Bureau of Reclamation
- Memo, To Tom Shrader from Bill Weisenborn, "Yearly resource management expenditures along LCR by federal agencies", 16 August, 1988
- "Boulder Canyon Project O&M Cost History"
- "Visitor Services Revenues vs. O&M Expense"
DRAFT ORGANIZATIONAL ELEMENTS
Decision Makers